What is the schedule for irrigation upgrades?
Irrigation upgrades phase 1 will be on the front nine only this year. Nutt Irrigation company will be doing the install. Nutt will be on site by September 12th to inventory parts, fuse pipe and start to stake where Irrigation heads will be according to the architect plans. Nutt will start later that week on #9 installing the new system. Only one hole will be closed at a time unless transitioning from one hole to the next. The total project (phase 1) should be complete before the end of 2022.