Irrigation Update 3/8/23
Sod Work-We are in the final stages of completing the irrigation project on holes 1-9 and The Village Green. Sod work is nearing completion. Some areas may look a little different for a few months until the sod can take root and start blending in. I have attached two photos of bentgrass sod removal from 9 gold tee used to patch fairways, and of the fescue sod that has been installed in the rough areas.