Holes 10-12 are completed and hole 15 will be finished by Thursday! Attached are photos of the greens loop tie in at 15 green and main line install to 15 green.
The weather has finally cleared enough to resume working on the landslides. Tri County Construction will be working on 11 and 10 this week. The large pile of dirt is what is left of the blue tee on 11!