Irrigation Update 10-6-2023
All 6 underground bores were completed this week! Hole number 11 will be finished this weekend and we will move on to hole number 12 and to attaching the main line from 17 pumphouse to the rest of the project. We expect to pick up speed and have set the goal to complete one hole per week from here on out. Attached pictures are of tying main line into 11 pump house before and after.