Irrigation Update 10-26-2023

Image
We have finished number 14 and are over half way finished with 13. We have the other half of 13 then 16,17, and 18 remaining! Pictures are of 14 finished and 13 greens loop and main line install! 

Irrigation Update 10-17-2023

Image
Holes 10-12 are completed and hole 15 will be finished by Thursday! Attached are photos of the greens loop tie in at 15 green and main line install to 15 green. 

Irrigation Update 10-13-2023

Image
Irrigation install is complete through hole 12. Main line is now being installed on 13-15!

Irrigation Update 10-6-2023

Image
All 6 underground bores were completed this week! Hole number 11 will be finished this weekend and we will move on to hole number 12 and to attaching the main line from 17 pumphouse to the rest of the project. We expect to pick up speed and have set the goal to complete one hole per week from here on out. Attached pictures are of tying main line into 11 pump house before and after.